Going off the deep end with scaffolding…
The Princeton Medical Center at Plainsboro, NJ is adding on to their illustrious hospital with two new rehabilitation pools. The crews needed to get access to the ceiling to do some repairs and additions. Well, with swimming pools spanning the entire room it makes it a bit difficult to reach up that high.
So they called Pat McAndrew at Superior Scaffold and said, “Help.” Since they had spent most of their budget on these incredible pools they were looking for a low cost alternative to just scaffolding the entire pools all the way up to the ceiling. They also wanted to use Baker/Painter scaffolds to roll from one end of the pool area ceiling to another.
So, they creatively devised a plan that would put an 8’ scaffolding tower down into the center of the large pool from the 3’ shallow end down to the 9’ deep end. They used 8’ horizontal trusses at deck height and then ran aluminum joists from side walls to trusses at 16” centers. The entire thing was then topped off with a deck of ¾” plywood. This would allow the baker scaffold to roll freely around the entire room while allowing crews to reach to the ceiling. You can see just how wide and deep this room is.
Now, the small pool was a bit different. They rested aluminum joists on the concrete side walls at 16” centers and then topped that off with plywood. Since it was only 18’ in diameter the aluminum joists would be able to support all of the weight put upon them.
Bingo, bango, bongo… another Superior solution and satisfied customer. Superior specializes in creative solutions for scaffolding problems. Call 215 743-2200 to see what Superior can do for you.